| 1 | 4 | Yishi Guo | h2. Time line |
|---|---|---|---|
| 2 | 5 | Yishi Guo | |
| 3 | 5 | Yishi Guo | h3. First |
| 4 | 5 | Yishi Guo | |
| 5 | 1 | * Week 1 (23/05 ~ 29/05) |
|
| 6 | 5 | Yishi Guo | > Create test project for getting frames and selecting cameras. |
| 7 | 1 | * Week 2 (30/05 ~ 05/06) |
|
| 8 | 5 | Yishi Guo | > oF GUI for selecting cameras. |
| 9 | 3 | Yishi Guo | * Week 3 (06/06 ~ 12/06) |
| 10 | 3 | Yishi Guo | * Week 4 (13/06 ~ 19/06) |
| 11 | 3 | Yishi Guo | * Week 5 (20/06 ~ 26/06) |
| 12 | 1 | * Week 6 (27/06 ~ 03/07) |
|
| 13 | 1 | * Week 7 (04/07 ~ 10/07) |
|
| 14 | 5 | Yishi Guo | |
| 15 | 5 | Yishi Guo | h3. Second |
| 16 | 5 | Yishi Guo | |
| 17 | 4 | Yishi Guo | * Week 8 ... |