Wiki

Version 6 (Yishi Guo, 08/08/2011 07:54 pm)

1 4 Yishi Guo
h2. Time line
2 5 Yishi Guo
3 5 Yishi Guo
h3. First
4 5 Yishi Guo
5 1
* Week 1 (23/05 ~ 29/05)
6 5 Yishi Guo
> Create test project for getting frames and selecting cameras.
7 1
* Week 2 (30/05 ~ 05/06)
8 5 Yishi Guo
> oF GUI for selecting cameras.
9 3 Yishi Guo
* Week 3 (06/06 ~ 12/06)
10 3 Yishi Guo
* Week 4 (13/06 ~ 19/06)
11 3 Yishi Guo
* Week 5 (20/06 ~ 26/06)
12 1
* Week 6 (27/06 ~ 03/07)
13 1
* Week 7 (04/07 ~ 10/07)
14 5 Yishi Guo
15 5 Yishi Guo
h3. Second
16 5 Yishi Guo
17 4 Yishi Guo
* Week 8 ...
18 6 Yishi Guo
19 6 Yishi Guo
郭一实